IBPS Clerk Mains Quantitative Aptitude Questions 2019 (Day-21) High Level New Pattern

Dear Aspirants, Quantitative Aptitude plays a crucial role in Banking and all other competitive exams. To enrich your preparation, here we have provided New Pattern Aptitude Questions for IBPS Clerk Mains. Candidates those who are going to appear in IBPS Clerk Mains can practice these questions daily and make your preparation effective.

[WpProQuiz 4940]

Click Here for IBPS Clerk Mains Online Mock Test

Direction (1 – 5): Study the following information carefully and answer the given questions:

The table shows percentage of work done by each persons and time taken (Days) by each person to do that work.

1) A and B working alternatively starting with A and work for 28 days after that both are left and then the remaining work completed by C and E. If C and E work alternatively starting with C then how many days remaining work will be completed?

a) 17(1/2) days

b) 18(1/2) days

c) 20(1/2) days

d) 13(1/2) days

e) None of these

2) If D work with 25 % more efficiency for 4 days after that D left and then for 12 days B work with 40 % less efficiency and A work with 50% more efficiency together. Then the remaining work completed by another person F in 15 days. Find in how many days F can complete the whole work alone?

a) 120 days

b) 180 days

c) 140 days

d) 160 days

e) None of these

3) If E work with 25% more efficiency to finish the work and F takes 75% of the days which E takes to finish 125% of work. Efficiency of G is twice of E, in how many days will the work be completed if E is worked with F and G on alternative days starting with F?

a) 16(1/8) days

b) 14(1/8) days

c) 7(1/8) days

d) 9(1/8) days

e) None of these

4) Five persons A, B, C, D and E work alternatively in such a way that, on first day, A and B work together and on second day C, D and E work together, find in how many days whole work will be completed?

a) 11(1/2) days

b) 10(1/2) days

c) 12(1/2) days

d) 9(1/2) days

e) None of these

5) A, B, C and E completed a piece work costing Rs. 40600. If their daily wages are in the ratio of 5 : 7 : 12 : 6, then what amount will be received by A and E together?

a) Rs. 24000

b) Rs. 30000

c) Rs. 25000

d) Rs. 28000

e) None of these

Directions (6 – 10): The questions below are based on the given Series-I. The series-I satisfy a certain pattern, follow the same pattern in Series-II and answer the questions given below.

6)

a) 850

b) 900

c) 920

d) 825

e) 720

7)

a) 202

b) 196

c) 144

d) 112

e) 214

8)

a) 65

b) 73

c) 87

d) 53

e) 51

9)

a) 210

b) 187

c) 193

d) 171

e) 157

10)

a) 524

b) 612

c) 670

d) 718

e) 656

Answers:

Directions (1-5):

1) Answer: a)

Number of days A to complete the whole work alone=18*100/30=60 days

Number of days B to complete the whole work alone=15*100/60=25 days

Number of days C to complete the whole work alone=5*100/25=20 days

Number of days E to complete the whole work alone=20*100/40=50 days

A and B total unit of work = 300 unit

A complete the work in first day = 5 units

B complete the work in second day = 12 units

Total work completed after two days = 5 + 12 = 17 units

Both are working 14 and 14 days respectively

Work completed after 28 days = (5*14) + (12*14) = 238

Remaining work = 300 – 238 = 62

C and E total units = 100

First day complete C = 5 units

Second day complete E = 2 units

16 days = 5*8 + 2*8 = 56 unit complete after 16 days

Remaining unit = 6

17th day C complete 5 units of work

18th day E complete = 1/2 days

Total time = 16+1+1/2 = 17(1/2) days

2) Answer: c)

Number of days D to complete the whole work alone = 4*100/20 = 20 days

D 25% more efficiency = 20*100/125 = 16 days

D Work for only 4 days = 4/16 = 1/4

Remaining work = 3/4

Number of days A to complete the whole work alone =18*100/30 = 60 days

A 50% more efficiency = 60*100/150 = 40 days

Number of days B to complete the whole work alone = 15*100/60 = 25 days

B 40% less efficiency = 25*140/100 = 35 days

A+B work for 12 days complete the work = 12*(1/40 + 1/35)

= 12* [(7+8)/280]

= 3 * [15/70]

= 9/14

Remaining work = ¾ – 9/14 = 3/28

F completed 3/28 work in 15 days.

Whole work completed by F = (28/3)*15 = 140 days

3) Answer: b)

Number of days E to complete the whole work alone=20*100/40=50 days

E takes 25% more efficiency=50*(100/125) = 40days

F complete the whole work=40*(75/100)*(100/125) = 24 days

As efficiency of G is twice that of E so time taken by G = 20 days

LCM of (40, 24, 20) = 120

E complete = 3 units per day

F = 5 units

G = 6 units

First day work E and F together = 3 + 5 = 8 units

Second day E and G = 3 + 6 = 9 units

Two days work = 8+9 = 17 units

After 14 days work = 17*7 = 119 units

Remaining work = 1 unit, which is to be completed by E and F in 1/8 days

Total time = 14 + 1/8 = 14(1/8) days

4) Answer: a)

Number of days A to complete the whole work alone=18*100/30=60days

Number of days B to complete the whole work alone=15*100/60=25 days

Number of days C to complete the whole work alone=5*100/25=20 days

Number of days D to complete the whole work alone=4*100/20=20 days

Number of days E to complete the whole work alone=20*100/40=50 days

LCM of (60, 25, 20, 20 and 50) = 300

A complete =5 units

B = 12 units

C = 15 units

D = 15 units

E = 6 units

First day work of A and B = 5 + 12 = 17 units

Second day work C, D and E = 15 + 15 + 6 = 36 units

First two days work = 17 + 36 = 53 units

First 10 days work = 53*5 = 265 units

Remaining =300 – 265 = 35

11th day = 17 units

Remaining work = 35 – 17 = 18 units

12th day = 18/36 = 1/2

Total work = 11(1/2) days

5) Answer: a)

Number of days A to complete the whole work alone=18*100/30=60days

Number of days B to complete the whole work alone=15*100/60=25 days

Number of days C to complete the whole work alone=5*100/25=20 days

Number of days E to complete the whole work alone=20*100/40=50 days

Ratio of wages = 5*60 : 7*25 : 12*20 : 6*50

= 300 : 175 : 240 : 300 = 60 : 35 : 48 : 60

(A + E)’s wages = 40600*(120/203) = Rs. 24000

Directions (6-10):

6) Answer: a)

Series I pattern:

1549 – 192 (361) = 1188

1188 – 172 (289) = 899

899 – 152 (225) = 674

674 – 132 (169) = 505

505 – 112 (121) = 384

Series II pattern:

2015 – 192 (361) = 1654

1654 – 172 (289) = 1365

1365 – 152 (225) = 1140

1140 – 132 (169) = 971

971 – 112 (121) = 850

7) Answer: d)

Series I pattern:

14 * 2 + 2 = 28+2 = 30

30 * 2 + 4 = 60 + 4 = 64

64 * 2 + 8 = 128 + 8 = 136

136 * 2 + 16 = 272 + 16 = 288

288 * 2 + 32 = 576 + 32 = 608

Series II pattern:

3 * 2 + 2 = 6 + 2 = 8

8 * 2 + 4 = 16 + 4 = 20

20 * 2 + 8 = 40 + 8 = 48

48 * 2 + 16 = 96 + 16 = 112

112 * 2 + 32 = 224 + 32 = 256

8) Answer: b)

Series I pattern:

137 + 15 = 152

152 + 20 = 172

172 + 25 = 197

197 + 30 = 227

227 + 35 = 262

Series II pattern:

73 + 15 = 88

88 + 20 = 108

108 + 25 = 133

133 + 30 = 163

163 + 35 = 198

9) Answer: c)

Series I pattern:

Series II pattern:

10) Answer: d)

Series I pattern:

153 – 1 = 3374

133 – 3 = 2194

113 – 5 = 1326

93 – 7 = 722

73 – 9 = 334

53 – 11 = 114

Series II pattern:

193 – 1 = 6858

173 – 3 = 4910

153 – 5 = 3370

133 – 7 = 2190

113 – 9 = 1322

93 – 11 = 718

Click Here for IBPS Clerk Mains Online Mock Test

Daily Practice Test Schedule | Good Luck

Topic Daily Publishing Time
Daily News Papers & Editorials 8.00 AM
Current Affairs Quiz 9.00 AM
Current Affairs Quiz (Hindi) 9.30 AM
NIACL AO Prelims – Reasoning 10.00 AM
NIACL AO Prelims – Quantitative Aptitude 11.00 AM
Vocabulary (Based on The Hindu) 12.00 PM
NIACL AO Prelims – English Language 1.00 PM
SSC Practice Questions (Reasoning/Quantitative aptitude) 2.00 PM
IBPS Clerk – GK Questions 3.00 PM
SSC Practice Questions (English/General Knowledge) 4.00 PM
Daily Current Affairs Updates 5.00 PM
SBI PO/IBPS Clerk Mains – Reasoning 6.00 PM
SBI PO/IBPS Clerk Mains – Quantitative Aptitude 7.00 PM
SBI PO/IBPS Clerk Mains – English Language 8.00 PM

Leave a Reply

Your email address will not be published. Required fields are marked *

slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot slot slot slot slot slot slot slot slot slot slot slot slot slot slot slot slot slot slot slot slot slot slot slot slot slot slot slot slot gacor slot777 slot slot gacor slot777 slot slot gacor slot777 slot slot gacor slot777 slot777 olxtoto badak178 bro178 nagawin jagoledak slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor slot gacor indo178 garuda55 badak178 slot88 indo66 slot88 slot88 rajabotak dwg288 inatogel NAGAHOKI88 Dwg288 nagawin dewi11 badak178 rajatogel slot qris inatogel dwg288 mahjongjp88 rajabotak badak178 dwg288 slot777 api66 bro178 rajabotak angkabet dwg288 dwg288 badak178 watitoto danatoto slot mahjong badak178 mawartoto olxtoto watitoto danatoto dewi11 indo66 slot777 olxtoto asia66 jagoledak dewi11 idamantoto olxtoto mawartoto koitoto dewi11 dewi11 apinaga depobos nagawin badak178 jagoledak wdbos indo178 bro178 wdbos musang178 watitoto danatoto jnetoto evostoto hondatoto slot maxwin slot gacor api66 bro178 watitoto indo178 slot777 slot gacor slot maxwin watitoto slot gacor slot maxwin slot88 depobos wdbos badak178 musang178 jagoledak angkabet inatogel api66 hondatoto rupiahtoto watitoto indo178 rajabotak